In Primavera P6, baselines are saved copies of the project plan. When you save a baseline, you’ll be saving a version of the project as it is – at the current point in time. With baselines, you can compare variances and changes as your project progresses over time. However, you can not open and interact with baselines. They stay tied to the original project file, and you can’t open them up as if they are another project. Instead, you can view baseline data alongside your current project data using bars in the Gantt Chart and columns in the table.

However, there may be times when you need to share a baseline copy of your project with others. By default, you can’t export baselines – instead, you can only export the entire project file. If you want to export out a single baseline, separate from the project, you will need to first restore the baseline. This allows you to detach the baseline from the original schedule and work with it as if it were another project all together.

In this article, we will cover how to restore baselines in Primavera P6. The following examples are all from Primavera P6 Professional 23. However, these tools are available in all versions of P6.

What Are Baselines?

Baselines are saved copies of the project plan. Creating a baseline is similar to pressing “Save As” – it will save a copy of the project as it is at a certain point in time. When scheduling in Primavera P6, you’re working with one project file from beginning to end. The program saves on its own, so there is no need for you to manually save the project. However, once your project actually begins, you will begin updating it with actuals. When performing status updates, you’ll want to have a saved copy of your project plan to look back at. This will show whether your project is on track, ahead, or behind schedule. You can do this by saving baselines. 

Saving a baseline does not create another project file. Instead, the baseline will save within the current project file. You can not open up and work with a baseline like you can with the current project. Instead, baseline data will display in columns in the table and bars in the Gantt Chart. With these fields, you can compare the updated project with the original project plan. The baseline will stay saved to the project file, and you can even export it with the project as well.

Creating Baselines

You can create as many baselines as needed in Primavera P6. We recommend creating your first baseline after adding all data to the project, but before the project begins. Additionally, you should create additional baselines after every status update. 

You can create a baseline at any time in Primavera P6 by selecting Project > Maintain Baselines. Select Add to add a new baseline. You can either choose to save the current project as a new baseline, or convert another project to be a baseline of the current one. Once saved, the baseline will appear within the Manage Baselines window.

Hold shift key to keep line markup tools straight in Bluebeam Revu 2019

Restore Baselines

With a baseline saved, you can now assign it to view baseline data within the activity table and the Gantt Chart. However, you can not open up the baseline as if it were a separate project. The baseline will save to the current project file – rather than as a separate project file. You can not export the baseline project separately from the current project file. However, there is a tool available to separate the baseline from the current project: Restore Baselines.

In Primavera P6, restoring a baseline will disconnect it from the current project file. This process will convert the baseline into a separate project within P6. Once converted, you can work with this former baseline the way you would any other project. You can add or delete activities, adjust relationships, and even export the project to share it with others. If you need to share a baseline project with others, you’ll need to restore the baseline in order to export it.

To restore a baseline, select Project > Maintain Baselines. Select the desired baseline and press Restore. Within the warning window, select Yes to continue.

Hold shift key to keep line markup tools straight in Bluebeam Revu 2019

Once completed, the baseline will disappear from the Manage Baselines window. The baseline will now be available as a separate project, accessible from the Projects screen. The new project will appear within the same EPS layer as the project it was created from. The Name and ID of the project will include “B1” at the end of it – indicating that this is a former baseline. You can now open and work with this project by right clicking on it and selecting Open.

Hold shift key to keep line markup tools straight in Bluebeam Revu 2019

Now, you can work with this baseline project separately from the original project. Adjustments made in the baseline project will not affect the original project, or vice versa. Now, this baseline will act just like a separate project.

Exporting Restored Baselines

With the baseline restored into a separate project, you can now export it to share it with others. To do this, first open up the restored baseline in Primavera P6. Then, select File > Export. Use the Export window to select the settings needed for your project. 

Hold shift key to keep line markup tools straight in Bluebeam Revu 2019

Once completed, you’ll have an exported version of the baseline saved to your computer. You can now share this project via cloud, network drive, or email. Recipients can import the project into their own scheduling programs to work with it further.

Converting Restored Baselines into Baselines

With a baseline restored, you can turn it back into a baseline at any time. This will reattach the baseline to the original project, allowing you to assign it and use it in comparisons once again. If you restored the baseline solely to export it, you may want to do this afterwards to be able to access it as a baseline once again.

To convert a restored baseline back into a baseline, open up the project you originally created the baseline from. Select Project > Maintain Baselines and select Add to create a new baseline. Here, you’ll have two options for creating a new baseline. You can create a new baseline of the current project, or convert another project to be a baseline of the current one. This time, select the latter option of Convert another project to a new baseline of the current project.

The Select Project window will open, allowing you to choose a project to create the baseline from. Select the project that you restored earlier, and press Assign. The baseline will appear under the Maintain Baselines window. This process will convert the project into a baseline – therefore, it is no longer available or accessible from the Projects screen. Now, you have the baseline attached to the project once again – just as it was before you restored it.

Hold shift key to keep line markup tools straight in Bluebeam Revu 2019

Summary

In Primavera P6, baselines are saved copies of the project schedule at a certain point in time. Creating a baseline is like pressing Save As – it allows you to save the project as it currently is. However, baselines do not save as separate project files. Baselines remain a part of the original project file, and you can only view them using columns in the table and bars in the Gantt Chart. This can make it difficult to share baseline data with others, as you can’t export it the way you would another project. Luckily, P6 allows you to restore baselines. Restoring a baseline will separate it from the current project file, saving it as a separate project all together. After restoring a baseline, you can then export it out and share with others – separate from the original project. Lastly, if you decide you want to reattach the baseline and the project, you can do this as well. After restoring a baseline, you can convert it back into a baseline and reattach it to the original project. In this way, you can work with baselines both as baselines and as separate projects.

If you have any comments, questions, or suggestions, please use the comment section on the bottom of this page. Don’t forget to subscribe to our blog to get more Primavera P6 tips & tricks directly in your inbox!

Lauren Hecker is a Primavera P6, Oracle Primavera Cloud, and Microsoft Project instructor for Taradigm. To see her next open enrollment course, please visit our calendar. To schedule an onsite or custom course, please contact us!