At any time, you can print your schedule in Oracle Primavera Cloud using the Print button. This is vital, as many contracts require you submit PDF printouts of the schedule for review. By printing, you can share project data with users outside of your OPC database – without having to provide them with the project file. You can’t print every page in OPC – you can only print those with a print icon displaying. However, the print button is available on most pages that you would need to print – such as the Activities page.

Access Preferences in the Revu menu in Bluebeam Revu 2019

When printing for the first time in OPC, you may run into color issues. Sometimes, even when your print preview features colors, the print out will appear in black and white. This can be detrimental, as you won’t be able to differentiate between activities and WBS layers. However, there is a very easy solution to this problem: turning on Background Graphics.

In this article, we will look at what to do if colors aren’t printing correctly in Oracle Primavera Cloud. 

Preparing for Printout

To print a schedule in Oracle Primavera Cloud, you will first need to open up the page you would like to print. Typically, the page you’ll need to print most often is the Activities page. Here, you’ll be able to show all work needed to complete the project, along with a timeline of how long it will take. To navigate to the Activities screen, first open up a project using the Object Selector. Within the Main Menu, select Schedule > Activities.

Access Preferences in the Revu menu in Bluebeam Revu 2019

Before printing, you will want to set up the Activities page for printing. When you print in OPC, the printout will show data exactly as it displays on the screen. Only the columns currently displaying in the table and the bars currently displaying in the Gantt Chart will show in the printout. Therefore, you should make any adjustments to your View before printing. You can do this by opening up a previously saved View, or by manually adjusting the display. You’ll even want to make adjustments to the size of the columns – as these will show up in the printout as well.

After making all needed adjustments to your View, you can select the Print button to see the Print Preview.

Access Preferences in the Revu menu in Bluebeam Revu 2019

Print Preview

Within the Print Preview, you can view the current print output. On the left side of the screen, you can view the pages you will be printing. You can click through these pages to view the display of each page. On the right side of the screen, you can adjust settings for the printout – such as the page size and scaling. 

Access Preferences in the Revu menu in Bluebeam Revu 2019

If you hover over the print preview, you’ll find more page editing options – such as Edit Content, Edit Header, and Edit Footer. Selecting any of these options will give you a new set of settings on the right side of the screen. Here, you can ensure that your printout has all the data necessary to paint a clear picture of the schedule.

Access Preferences in the Revu menu in Bluebeam Revu 2019

Once you’ve adjusted these print settings, select Print. Within your browser, a new print window will open, allowing you to choose a printer. However, it’s here that you might notice that the print preview has changed. Unlike the previous page, this print preview may display without any colors for the table and the Gantt Chart. This may happen even if the color settings are set to Color – rather than Black & White. This is a common print issue that has a very easy solution: turning on Background Graphics.

Access Preferences in the Revu menu in Bluebeam Revu 2019

Background Graphics Option

Within your browser’s print window, you should find a variety of options – such as Destination and Pages. You will also find additional options under a header called More Settings. Depending on your internet browser, this may display with different text. Under More Settings, you’ll find a section for Options. Here, you’ll find a checkbox for Background graphics. Check this option, and the colors will all return to the print preview.

Access Preferences in the Revu menu in Bluebeam Revu 2019

Although the Background graphics option is turned off by default, this setting will save once you turn it on. Moving forward, you won’t need to worry about adjusting this setting again. Now, all your printouts will look exactly like they do within the Print Preview.

After adjusting your Print settings, you may want to save your View using the Manage Views menu. All print settings – including the content, header, and footer, will save to your View. Now, you can apply this View to any project to create a perfect printout without needing to make any additional adjustments.

Access Preferences in the Revu menu in Bluebeam Revu 2019

Summary

When printing in Oracle Primavera Cloud, you might run into some color issues. Commonly, the first time you print in OPC, colors will not display properly. Instead of Gantt Chart bars and grouping bands appearing in their set color, they will display in black and white. This issue occurs when Background Graphics is turned off – which is the default setting. To fix this issue, turn on the Background Graphics option under your Print settings when printing. After making this adjustment, it will stay on moving forward. Now, you can print your project exactly the way you need using Oracle Primavera Cloud.

If you have any comments, questions, or suggestions, please use the comment section on the bottom of this page. Don’t forget to subscribe to our blog to get more Oracle Primavera Cloud tips & tricks directly in your inbox!

Lauren Hecker is an Oracle Primavera Cloud, Primavera P6, and Microsoft Project instructor for Taradigm. To see her next open enrollment course, please visit our calendar. To schedule an onsite or custom course, please contact us!